24 November 2026
Work starts on Barkham Solar Farm site
Initial work has begun, ahead of the main construction programme starting next year
Work has started to build Barkham Solar Farm, marking the next stage of a project that will generate renewable electricity and provide income to support Wokingham Borough Council services.
Scottish and Southern Electricity Networks (SSEN) has confirmed that the solar farm can be connected to the electricity network from September 2027, for both the distribution and transmission elements of the project.
Once connected next year, all the renewable electricity generated by Barkham Solar Farm will be fed into the national electricity grid.
This connection date gives the council and its construction partner, Equans, a clear timetable for delivering the solar farm and bringing it into operation.
The new offer resolves the previous uncertainty around the project’s transmission connection and provides connection dates for both the distribution and transmission networks, allowing the wider delivery programme to progress with greater certainty.
People travelling along Barkham Ride will begin to see activity on the site from mid-November.
What's happening now
The first phase will include creating the site entrance, establishing the construction compound and carrying out other preparatory work.
These enabling works will prepare the site for the main construction programme, which is due to begin next year.
This is when the solar panels and associated infrastructure will start to be installed.
The council appointed Equans to build the solar farm on council-owned farmland to the north of California Country Park, west of Finchampstead and south of Barkham.
Once operational, Barkham Solar Farm is expected to generate about 28,500 MWh of renewable electricity each year, enough to meet the annual electricity needs of approximately 9,400 average UK homes.
Generating income and reducing emissions
After covering the cost of financing the project, it is forecast to generate a surplus of more than £1million a year for the council.
This income will help support essential services during a period of significant financial pressure.
The project is one of the key commitments in the council’s Climate Emergency Action Plan and supports its wider Climate and Nature Strategy.
It will help reduce carbon emissions by generating electricity locally while supporting the borough’s transition towards carbon neutrality.
The project was previously delayed following national changes to the process for securing electricity grid connections.
Connection confirmed
The date now confirmed by SSEN provides greater certainty about when the renewable electricity generated on site can begin feeding into the network.
As is usual for a major grid connection, some detailed design and routing matters will continue to be worked through with SSEN as the project progresses, with any resulting changes managed through the normal contractual process.
Cllr Imogen Shepherd-DuBey, executive member for finance and governance, said: “Starting work on site is an important milestone for Barkham Solar Farm.
“Residents will soon begin to see the site entrance and construction compound taking shape, ahead of the main construction programme beginning next year.
“The new grid connection date gives us a clear timetable for delivering the project and beginning to realise its environmental and financial benefits.
“This is a long-term investment in cleaner energy, the council’s financial resilience and the future of the borough.”
Gregory Allouis, Energy Solutions Director at Equans UK & Ireland, said: “Seeing work begin at Barkham is an important milestone and reflects the strong partnership between Equans and Wokingham Borough Council in moving this ambitious project forward.
“Through our expertise in delivering solar infrastructure, we will help create a reliable renewable energy asset that generates clean power locally, supports biodiversity and delivers lasting environmental and financial value for the borough.”
Greener and better prepared
Barkham Solar Farm forms an important part of the council’s work to make Wokingham Borough greener and better prepared for the future.
The council’s Climate and Nature Strategy sets out how climate change is already affecting the borough through hotter summers, increased flood risk and less predictable weather.
It focuses on practical action, including generating clean energy locally, improving buildings, making greener travel easier and protecting parks, wildlife and the wider countryside.
Cllr Lou Timlin, executive member for climate emergency, community safety and public protection, said: “Barkham Solar Farm shows how our climate commitments are being turned into practical action.
“It will generate renewable electricity locally, reduce reliance on fossil fuels and support nature through new woodland, trees, hedgerows and grassland.
“The start of work on site is a significant step forward. This project will help us cut carbon emissions, improve biodiversity and prepare the borough for the future, while also generating income to support council services.”
Wider plans and investment

See a larger version of the diagram.
The 52-hectare solar farm will include approximately 43,000 solar panels and the equipment needed to generate and distribute electricity.
Fencing, CCTV and other security measures will also be installed. Planning permission for the project was approved in 2022.
Alongside the renewable energy infrastructure, the project will deliver improvements to walking and cycling connections and the surrounding natural environment.
A new Greenway will run through the site, connecting with the proposed extension to Rook’s Nest Wood to the north and California Country Park to the south.
It will help connect Arborfield and Finchampstead with Barkham village, providing an attractive, traffic-free route and making it easier for residents to walk and cycle around the area.
New crossings, grasslands and tree planting
A signal-controlled pedestrian crossing will be installed where the route crosses Barkham Ride.
The project will also create 2.66 hectares of woodland to the south of the site, alongside meadow grassland, new hedgerows and additional tree planting.
These measures will improve biodiversity and help capture carbon.
The council has already worked with local charity Freely Fruity to plant approximately 1,000 fruit trees on the site.
The council will continue to provide updates as work progresses, including advance information about any disruption affecting journeys in the area.
Residents can find more information on the Barkham Solar Farm project webpage and check One.Network through the council’s roadworks page for current and planned roadworks.