This is an information request relating to the cost of roundabout installations. Please include the information for each of the following financial years; 2019/20, 2020/21, 2021/22:

1. A list of roundabouts installed by the council including their locations
The following roundabouts have been built as part of wider projects in the time periods specified.

• Waterloo Road, Wokingham (as part of the new South Wokingham Distributor Road)
• A329 Reading Road junction with the new North Wokingham Distributor Road
• A329 Reading Road junction with the new Winnersh Relief Road
• A327 Reading Road northern junction with Observer Way, Arborfield
• A327 Eversley Road southern junction with Observer Way, Arborfield

2. The expected budget of each roundabout, when the project was initially begun, and the final cost upon completion
The Council has installed 5 roundabouts during the specific timeframes requested. However, we do not hold the information specifically requested.

None of the roundabout junctions have been constructed as standalone projects as they all form part of wider works. As such we do not hold specific costs for these junctions alone, either as a preconstruction budget or as a completed scheme. It would exceed the appropriate limit to review the material to see if the costs for the roundabout could be extracted from the overall project costs.