[Skip to content]

Barkham Bridge

Barkham Bridge

Schedule of work

  1. Summer / Autumn 2018: Data collection including archaeological and environmental studies
  2. Spring 2019: Complete detailed design    
  3. Spring 2019: Site preparation and utilities re-routing
  4. Autumn 2019: Construction begins
  5. Spring 2021: Open for traffic 
          

Current project status

Detailed design of the schemes is nearly complete, pending feedback from Thames Water and the Environment Agency and main construction is scheduled to begin late Autumn 2019 with the road due to be open to traffic in Spring 2021.

Watch the fly-through video

Watch the video, below, showing the route currently being constructed as part of the Arborfield Cross Relief Road and works at Barkham Bridge. This is being delivered by us as part of our £124 million Major Highways Project.

Why we're proposing improvement to Barkham Bridge

The current Barkham Bridge is an existing highway structure along B3349 Barkham Road, operating on a priority give-way system thereby enabling vehicular traffic to cross the Barkham Brook. The improvements as currently proposed include the construction of a new highway bridge in order to accommodate continuous flow 2 way traffic. These improvements are needed in order to support major new developments in Wokingham borough, in particular the Arborfield Garrison major development.

Background

The Barkham Bridge project consists of a new bridge structure across the Barkham Brook and approximately 300 metres of associated carriageway realignment. The new bridge is to be constructed south of the existing Barkham Bridge within private land. The existing Barkham Bridge Structure is to be retained and be converted to a shared footway/cycleway, connecting the existing sections of footway to the east and west.

Barkham Bridge is being progressed through permitted development rights under the Town and Country Planning Act 1990 as the proposed works are on public highway or immediately adjoining public highway. 

A certificate of lawful development under Section 192 of the Act was provided by the planning authority in February 2017.

We are currently working closely with the Environment Agency to confirm details around flood mitigation and drainage, with the aim of getting these fully approved and signed off over the summer.

Main construction is due to start in Autumn 2019. A detailed construction programme is currently being developed.

A key part of the programme will be coordinating with existing utility suppliers including gas, electricity, water, and other providers to ensure all utilities within the proposed works corridor are diverted or protected as necessary.  This will be carried out with minimal disruption to road users.

To stay up to speed with all our Major Highways projects you can sign up to our Major New Roads Newsletter which offers you a summary of all the latest progress that we have made from planning applications to construction.

For more detailed updates about the Winnersh Relief Road Phase 2:

Was this page useful?
Back to top