Greenways Route B will connect Cantley Park to Arborfield Cross via Woosehill. A public consultation on Route B was undertaken in March to May 2019 to consider the concept of the whole route. Secondary public consultations for separate sections of the route are also being undertaken once the designs have been further developed.
Take a look at the consultation document below:
The route has now been split into four sections. Take a look at the map of the full route below:
Section 1 – Cantley Park to Woosehill via Matthewsgreen
In Summer 2020 we consulted on an amended route for this section of the greenway through Cantley Park and Matthewsgreen. Take a look at the consultation documents below:
Construction at Cantley Park commenced in February 2021 and was completed in May 2021. Take a look at the photos of construction at Cantley Park below:
A statutory consultation was undertaken for the bridleway creation along the Jubilee Avenue section of the route. Following this consultation, we are now in discussion with residents about continuing the route from Milton Road before we make a decision on a bridleway creation order.
The design for a zebra crossing at Milton Road is also being developed and this will be installed once the design for the route at this point is resolved.
Take a look at this section of the route below:
Section 2.1 – Woosehill Meadows from Reading Road to Heron Road
A public consultation was undertaken in March to April 2021 for the Woosehill Meadows section of the route. Take a look at the consultation document below:
Thank you to everyone who took part in this consultation. The consultation report has now been published which details the comments received and the changes that have been made in response to these comments. The report and appendices can be downloaded below.
We've completed the detailed design for the route and chosen a contractor to construct it. Works are due to start after 6 May 2022, beginning at Heron Road and working northwards.
We are liaising with the South East Rivers Trust to coordinate works on Woosehill Meadows with their own planned works to avoid any conflicts. The main works are expected to be completed by the end of July, with some works relating to the construction of the new bridge at the north of Woosehill Meadows to be undertaken in September.
You can see more detail of the route in the design drawings below:
Please also see below a letter which was sent to Woosehill Meadows residents in early April to explain the works programme in more detail:
Section 2.2 – Heron Road to Bearwood Road via Foxhill
Negotiations and discussions are still underway with landowners regarding this section, as we are seeking opportunities for an alternate route in this area. Whilst negotiations are underway it is not possible to develop a detailed plan for construction.
Take a look at the route below:
Section 3 – Coombes Lane and Coles Lane
An initial design has been developed for a partial closure of this lane to facilitate the greenway. Consultation with adjacent landowners raised concerns about the private access to land adjacent to the lane and issues with the proposed closure. This has led to an adjustment of the design which will not require a closure of the route for vehicles.
This will be kept under review to ensure that the route remains suitable and safe for walkers, cyclists and horse riders. The route has been redesigned to cater for occasional vehicle traffic and agricultural traffic that use the lane.
The bridge at the Coles Lane ford will also be improved to facilitate an accessible crossing point for mobility restricted users.
It is expected that work on the bridge foundations will start in August 2022 and be completed by September 2022. The bridge can be built in October 2022 and the path itself can be built between April and August 2022.
This section of the route will be built in three phases:
Phase 1: Coombes Lane residential
The design for resurfacing of the tarmac surface of this lane is underway and will be included in our general resurfacing programme, which starts in May 2022.
Phase 2: Coombes Lane woods
The design for the surfacing on this section is finished and we are aiming for construction works to start in early summer 2022.
Phase 3: Coles Lane
A contractor has been appointed to design a replacement foot bridge for the Coles Lane ford. Design for the surfacing of the path is being finalised. No firm start date can be given for construction yet because the schedule depends on commissioning ground investigation surveys for the bridge. However, we are hopeful that it can begin in July or August 2022.