The Core Strategy in the Local Development Framework sets out the long term vision and strategy for
controlling development within an area.
For Wokingham Borough it will cover the period 1 April 2006 to 31 March 2026. The Council has agreed the following timetable for producing the Core Strategy:
Consult on the Initial Options from 15 June to 27 July 2005
Executive consider responses to the Alternatives for the Draft Core Strategy and agree submission document - 27 July 2006. The Executive deferred agreeing the submission Core Strategy.
Executive consider revised responses to the Alternatives for the Draft Core Strategy and agree submission document - 26 June 2008
Submit Core Strategy to the Secretary of State - 20 August 2008
Pre-Examination Meeting - 20 January 2009
Examination - Opens 17 March 2009
Receive binding Inspector's Report - June 2009
Adoption - July 2009